MGA Research
Nov 17, 2026
How operating authority, landing arrangements, marine approvals and contractual capacity rights fit together for investors, operators and purchasers.
MGA Lawyers | Telecommunications and digital infrastructure | Public-source review: 18 November 2026
A submarine cable project becomes commercially useful when its physical system, operating authority and contractual rights work together. Landing the cable is one milestone. Delivering capacity that customers can lawfully use, maintain and rely on requires a wider chain of arrangements: the Indonesian network operator, landing station, marine route, terrestrial connection, equipment and service obligations.
For sponsors, operators and capacity purchasers, the practical starting point is a responsibility map. Identify who owns each asset, who operates each network segment, who holds the relevant approvals, and who promises the customer a working service. Those roles may overlap, but the agreements should make the allocation explicit.
Identify the regulated activity
Indonesia distinguishes telecommunications networks, telecommunications services and special telecommunications. Article 9 of the Telecommunications Law also distinguishes network operation from services delivered using network infrastructure. The starting legislation is Law 36/1999, read with the amendments enacted through Law 6/2023. Telecommunications Law; Law 6/2023.
The commercial label therefore needs to be tested against the proposed activity. A company buying connectivity for its own business, an operator selling transmission capacity, and a provider delivering an internet service raise different questions. Assess the network configuration, the product sold, the customers served and the party exercising operational control before selecting the licensing route.
Dark fibre also requires attention. Article 3 of Ministerial Regulation 5/2021 requires the relevant closed fixed-network business authorisation for parties owning unlit cable networks for rental. Removing active equipment does not, by itself, resolve the regulatory classification. Regulation 5/2021, Articles 2–3.
Structure the Indonesian landing and operating role
For an overseas business providing international submarine transmission facilities directly into Indonesia, Articles 13–18 of Regulation 5/2021 establish a cooperation and landing-right framework involving an Indonesian telecommunications network operator. The operator's role includes substantive decision-making and operational control over the Indonesian cable system, together with landing-station and traffic responsibilities. Article 15(1)(d) specifically addresses full rights and authority as controller in decisions concerning the system in Indonesian territory. Regulation 5/2021, Articles 13–18.
The newer Komdigi Regulation 15/2025 repeats the international SKKL landing-right requirements in Annex II. These include operator eligibility, consortium participation and investment, control, and the relevant business authorisation. This is a substantive operating structure to establish before installation and commercial commitments are locked in. Regulation 15/2025, Annex II, international SKKL landing rights.
In practical terms, consortium governance, operating procedures, access rights and landing arrangements should tell the same story. A contractual title such as “landing party” is insufficient if another document prevents that party from performing its regulatory responsibilities.
Use the current OSS framework
Government Regulation 28/2025 replaced Government Regulation 5/2021. It distinguishes basic requirements, business licensing and supporting business approvals, with licensing outcomes determined by risk. An NIB should therefore be checked alongside the applicable licence or standard certificate, its verification status and any supporting approval. Existing permissions and applications also require a transition check. Regulation 28/2025, Articles 4, 12, 130–133 and 547–550.
KBLI classification must match the actual scope. OSS now provides KBLI 2025 conversion guidance; a historical code should not simply be carried into a new application without checking its current description and scope. Network operation, service provision and construction should be assessed separately where the business performs different activities. OSS KBLI conversion guidance.
Connect the marine route to the shore
Marine spatial conformity and telecommunications landing rights answer different questions. Regulation 28/2025 addresses KKPRL for continuing use of marine space, including seabed use, and requires location and activity information. Its criteria include continuous use for at least 30 calendar days. Regulation 28/2025, Articles 65–67.
Marine spatial assessment considers the applicable plans, conservation, fisheries, defence interests and existing uses. Ministerial Decision 14/2021 establishes submarine pipeline and cable corridors. Project teams should assess route alignment and the required project approvals together; a published corridor is not the project's own approval. KKP Regulation 28/2021, Articles 113–125; Decision 14/2021.
At the shore, identify the beach crossing, landing-station site and backhaul route as separate work packages. Land access, buildings, environmental coverage and marine works interfaces should follow the actual footprint. A new station and a connection into an existing station can have materially different requirements. The useful deliverable is a project-specific approval matrix with responsible parties and dependencies, rather than an undifferentiated list of permits.
Screen environmental requirements early
Government Regulation 22/2021 provides for AMDAL, UKL-UPL or SPPL according to the applicable criteria. Article 5 addresses significant impacts, scale and protected-area location; Article 20 provides for screening. The project should assess installation methods and associated facilities together, including relevant shore works and supporting infrastructure. It should not assume that every cable requires the same environmental document, or that an existing facility's approval automatically covers an expansion. Regulation 22/2021, Articles 4–5 and 20.
The timing matters commercially. Route or construction changes can affect the assessment, cost and delivery programme. Contract milestones should allow the required environmental process to be completed before the corresponding works begin.
Define exactly what an IRU provides
An indefeasible right of use is a contractual allocation of use rights. Its name alone does not establish ownership of the cable, a government permission or authority to operate a regulated network. Those questions require separate review of the agreement, asset arrangements and applicable law.
Specify whether the purchase concerns fibre pairs, wavelengths or managed capacity; identify the segments and endpoints; and explain the equipment and other inputs needed to use it. Address the term, transfer restrictions, maintenance contributions, upgrade decisions, outage treatment and consequences if the underlying system or operating arrangement ends.
For example, a hypothetical purchaser acquiring fibre between two landing stations may still need terminal equipment, power and onward connectivity. The contract should allocate those dependencies expressly. Price and nominal capacity are only part of the bargain.
Make service readiness measurable
Marine completion, technical acceptance, regulatory readiness and customer service commencement should be separately identifiable. Regulation 15/2025's wired-telecommunications standards include operational testing and the resulting SKLO process. Private acceptance evidence should be reconciled with the applicable regulatory steps. Regulation 15/2025, Annex I, wired telecommunications.
Define technical demarcation at named equipment or connection points. Allocate monitoring, fault isolation, repair coordination, power, access and escalation. Availability should describe what is being measured: an optical path, equipment power or an end-to-end service.
Before a major payment or service commitment, assemble a readiness record showing the relevant permissions, completed tests, available facilities and outstanding dependencies. This gives legal, engineering and commercial teams a common basis for deciding whether the promised capacity is ready to deliver.
This guide provides a general framework. The applicable requirements depend on the operating model, location, project scope and existing authorisations.